Gujarat Hybrid Renewable Energy Park: World’s Largest 30 GW Solar + Wind Case Study (Kutch, India)
- Green Fuel Journal

- 1 hour ago
- 22 min read
Gujarat Hybrid Renewable Energy Park Case Study: 30 GW Solar + Wind Power in Kutch, India
The Gujarat Hybrid Renewable Energy Park, also known as the Khavda Renewable Energy Park, represents humanity's boldest leap into sustainable energy infrastructure. Located in the salt desert of Kutch district, this unprecedented project is redefining the global renewable energy landscape. With a planned capacity of 30 GW combining solar and wind generation, this installation is set to become the world's largest renewable energy park—visible from space once completed.

The Gujarat Hybrid Renewable Energy Park is not merely a technical achievement; it embodies India's commitment to energy independence, carbon neutrality, and industrial transformation in the face of accelerating climate change.
How does a barren salt marsh, situated just one kilometer from the Pakistan border, transform into the epicenter of India's clean energy revolution? The answer lies in strategic vision, geotechnical innovation, and an unwavering commitment to the 500 GW by 2030 target.
This case study dissects the technical architecture, economic calculus, environmental implications, and operational realities of this giga-scale project currently taking shape across 72,600 hectares of wasteland in western Gujarat.
What Is the Gujarat Hybrid Renewable Energy Park?
Defining the World's Largest Renewable Energy Installation
The Gujarat Hybrid Renewable Energy Park is a hybrid solar-wind renewable energy complex under construction near Vighakot village in Kutch district, Gujarat, India. Officially approved by the
Government of Gujarat on September 9, 2020, and inaugurated with a foundation stone ceremony by Prime Minister Narendra Modi on December 15, 2020, this project represents the convergence of policy ambition, private capital, and technological prowess.
Key Technical Specifications:
Parameter | Value |
Total Planned Capacity | 30,000 MW (30 GW) |
Solar Capacity | 26,000 MW (26 GW) |
Wind Capacity | 4,000 MW (4 GW) |
Land Area | 72,600 hectares (726 sq km) |
Location | Khavda, Kutch District, Gujarat |
Distance from Border | 1 kilometer from India-Pakistan border |
Operational Capacity (as of 2025) | ~5,355 MW commissioned |
Target Completion | 2030 |
Expected Annual Generation | 81 billion units (81 TWh) |
Scale Comparison: Powering Entire Nations
To grasp the magnitude of this installation, consider that 30 GW of capacity is equivalent to:
The entire electricity generation capacity of Belgium (22 GW)
More than Switzerland's total installed capacity (20 GW)
Comparable to Chile's peak electricity demand
Sufficient to power approximately 18 million Indian households or 16.1 million homes continuously
The park's footprint of 726 square kilometers makes it:
Five times larger than Paris
Roughly the size of Singapore
Equal to 179,000 acres of contiguous renewable infrastructure
The "Waste Land" Concept: Turning Liability into Asset
The Khavda site occupies the Rann of Kutch, a vast salt marsh and seasonal desert characterized by:
Extreme salinity: Soil contains high concentrations of sodium chloride, rendering conventional agriculture impossible
Seasonal flooding: During monsoon, portions become waterlogged; water escape occurs only through evaporation
High albedo: Salt-white terrain reflects sunlight, beneficial for bi-facial solar panels
Minimal vegetation: Sparse flora due to saline conditions
Low population density: Remote location 70+ kilometers from nearest urban center
This "wasteland" designation under Gujarat's Waste Land Policy enabled large-scale land allocation without displacing agricultural communities or forests.
The Government of Gujarat mandated developers achieve 50% capacity within 3 years and 100% capacity within 5 years from road commissioning date (December 31, 2021).
Strategic Significance of the Gujarat Hybrid Renewable Energy Park
Contribution to India's 500 GW by 2030 Renewable Energy Target
At the COP26 climate summit in Glasgow (November 2021), Prime Minister Narendra Modi announced India's Panchamrit (five nectar elements) climate commitments:
Reach 500 GW non-fossil energy capacity by 2030
Meet 50% of energy requirements from renewable sources by 2030
Reduce carbon emissions by 1 billion tonnes by 2030
Reduce carbon intensity of GDP by 45% by 2030
Achieve net-zero emissions by 2070
As of January 2025, India's non-fossil fuel capacity stood at 217.62 GW, including:
119.07 GW solar power
52.14 GW wind power
11.60 GW bioenergy
8.80 GW nuclear power
Gap Analysis:
Remaining capacity needed: 500 GW - 217.62 GW = 282.38 GW by 2030
Annual addition required: ~47 GW/year through 2030
Khavda's contribution: 30 GW = 10.6% of remaining target
Single-project impact: Khavda alone provides 6% of India's total 500 GW commitment
This makes the Gujarat Hybrid Renewable Energy Park the single largest contributor to India's renewable energy roadmap from a greenfield project.
Shift from Fossil Fuel Dependency to Hybrid Renewable Models
India currently generates approximately 70% of its electricity from coal-fired thermal plants. This dependence creates:
Energy security vulnerabilities (coal imports cost $15-20 billion annually)
Air quality crises (Indian cities dominate WHO's most polluted rankings)
Carbon lock-in (existing coal plants have 20-30 year operational lifetimes)
The hybrid solar-wind model at Khavda addresses coal's limitations:
Fossil Fuel Challenge | Khavda Solution |
Fuel supply chain risk | Zero fuel requirement (sun + wind) |
Price volatility | Fixed generation cost over 25+ years |
Carbon emissions | 50 million tonnes CO₂ avoided annually |
Water consumption | Minimal (waterless robotic cleaning) |
Air pollution | Zero SOx, NOx, particulates |
By displacing 60,300 tonnes of coal daily when operational, Khavda reduces India's coal import bill by approximately $2.5 billion annually (at $100/tonne).
Project History, Policy & Institutional Framework
Timeline: From Concept to Commission
Date | Milestone |
April 2020 | Ministry of Defence grants security clearance for construction within 1 km of international border |
September 9, 2020 | Gujarat Government approves 60,000 hectares land allocation; initial proposal mentions 41.5 GW |
December 15, 2020 | PM Narendra Modi lays foundation stone |
December 31, 2021 | Completion of 16.26 km approach road + 40.83 km existing road widening |
February 2024 | 551 MW commissioned by AGEL |
March 2024 | 1,000 MW milestone achieved; 2.4 million photovoltaic modules installed |
July 2024 | First 250 MW wind power comes online |
August 2025 | NTPC Green commissions 212.5 MW |
October 2025 | GIPCL crosses 50% mark with 315 MW operational (target: 600 MW) |
November 2025 | Adani Group announces 1,126 MW / 3,530 MWh BESS project |
Current Status (Feb 2025) | ~5,355 MW operational capacity |
Projected Completion | 2030 (full 30 GW) |
Land Allocation Policy of Gujarat Government
The Gujarat Government's framework includes:
Waste Land Classification: Identifies non-agricultural, non-forest land unsuitable for cultivation
Lease Terms:
Long-term leases (25-30 years)
Nominal lease rates (~₹5,000-10,000/hectare/year)
Performance Milestones:
50% capacity within 3 years from road commissioning
100% capacity within 5 years
Penalties for non-compliance: lease cancellation
Transmission Coordination: State coordinates with Power Grid Corporation of India (PGCIL) for evacuation infrastructure
Institutional Roles: MNRE, SECI, GUVNL
Ministry of New and Renewable Energy (MNRE)
Policy Formulation: Sets national renewable energy targets, schemes (PM-KUSUM, rooftop solar)
Regulatory Oversight: Issues guidelines for competitive bidding, grid integration
Financial Support: Administers Viability Gap Funding (VGF), production incentives
International Coordination: Manages India's commitments under Paris Agreement
Solar Energy Corporation of India (SECI)
Tendering Authority: Conducts competitive reverse auctions for solar/wind capacity
Power Purchase Agreements: Signs long-term PPAs with developers
Risk Mitigation: Government guarantee backing reduces offtaker risk
ISTS Coordination: Facilitates Interstate Transmission System connectivity
Gujarat Urja Vikas Nigam Limited (GUVNL)
State Nodal Agency: Gujarat's primary power procurement utility
PPA Execution: Signs power purchase agreements for intra-state projects
Grid Integration: Coordinates with Gujarat State Load Dispatch Centre (GSLDC)
Technical Architecture: How Solar + Wind Hybrid Works
Complementarity Factor: Solar Peaks by Day, Wind by Night
The genius of the Khavda hybrid model lies in resource complementarity:
Diurnal Generation Pattern:
Time of Day | Solar Output | Wind Output | Combined Effect |
6:00 AM - 10:00 AM | Rising (30-70% of peak) | Declining (night breeze ending) | Moderate combined generation |
10:00 AM - 4:00 PM | Peak (90-100% capacity factor) | Low (5-15% capacity factor) | Solar-dominated |
4:00 PM - 8:00 PM | Declining (70-30% of peak) | Rising (afternoon/evening thermal gradients) | Transition period |
8:00 PM - 6:00 AM | Zero (nighttime) | Peak (60-80% capacity factor in Kutch) | Wind-dominated |

Kutch-Specific Meteorological Advantages:
Solar Irradiation: 2,060 kWh/m²/year (second-highest in India after Ladakh)
Wind Speeds: 8 meters/second average (5x higher than plains)
Clear Sky Days: 300+ days/year with minimal cloud cover
Coastal Influence: Proximity to Arabian Sea (~150 km) drives consistent wind patterns
Result: Capacity Utilization Factor (CUF) improves from:
23-25% (standalone solar)
30-35% (standalone wind)
38-42% (hybrid solar + wind)
This translates to 40-50% more electricity from the same land footprint.
Transmission Evacuation Infrastructure by Power Grid Corporation
Challenge: Moving 30,000 MW from remote Kutch to load centers (Mumbai, Delhi, industrial clusters) requires:
765 kV Ultra-High Voltage Transmission Lines:
Primary Corridor: Khavda → Bhuj → Sami → Vadodara → National Grid
Length: ~400 km dedicated transmission infrastructure
Investment: Ministry of Power allocated ₹18,598 crore ($2.2 billion) for 7 GW evacuation capacity
Capacity: Expandable to 30 GW through phased augmentation
Pooling Stations:
Khavda Pooling Station: Aggregates output from multiple developers
Voltage Step-Up: 33 kV (developer) → 220 kV (pooling) → 765 kV (interstate transmission)
Grid Stability Technologies:
STATCOM (Static Compensator): Reactive power management
HVDC Converters: Future-proofing for ultra-long-distance transmission
Wide Area Measurement Systems (WAMS): Real-time grid monitoring
Evacuation Bottleneck: Current constraint limits dispatch to ~5-7 GW until 2026-27 when Phase-2 transmission lines commission.
Capacity Allocation and Lead Developers
Zone-wise Allocation Breakdown
The Gujarat Hybrid Renewable Energy Park operates under a multi-developer model:
Developer | Capacity Allocated (MW) | Land Area (Hectares) | Technology Focus | Current Status (2025) |
Adani Green Energy Limited (AGEL) | 9,500 MW | 19,000 | Solar + Wind Hybrid | 5,355 MW operational |
Sarjan Realities Pvt. Ltd. (SRPL) | 4,750 MW | 9,500 | Solar + Wind Hybrid | Under development |
National Thermal Power Corporation (NTPC REL) | 4,750 MW | 9,500 | Solar + Wind Hybrid | 212.5 MW operational (Aug 2025) |
Gujarat State Electricity Corporation (GSECL) | 3,325 MW | 6,650 | Solar + Wind Hybrid | Under development |
Gujarat Industries Power Company Limited (GIPCL) | 2,375 MW | 4,750 | Solar | 315 MW operational (Oct 2025) |
Solar Energy Corporation of India (SECI) | 3,000 MW | 23,000 | Wind Only (competitive bidding zone) | Tenders issued |
Total | 27,700 MW | 72,400 hectares | - | ~5,882 MW operational |
Note: Remaining ~2,300 MW allocated for transmission corridors, roads, grid infrastructure.

Adani Green Energy Limited (AGEL): The Dominant Player
AGEL's Khavda Strategy:
Target Capacity: 9,500 MW within Khavda + additional 10,500 MW in adjacent zones = ~20,000 MW total in Kutch region
Investment Commitment: ₹1.5 lakh crore ($18 billion) by 2030
Operational Milestones:
March 2024: 1,000 MW commissioned
May 2025: 187.5 MW added
June 2025: 1,011.5 MW additional capacity
Current: 5,355 MW operational (as of mid-2025)
Technology Deployment:
55 million solar PV modules (bi-facial, 540-580 Wp)
1,000+ wind turbines (2.5-3.5 MW each)
Waterless robotic cleaning systems
Funding Partners:
TotalEnergies: $444 million equity for 1,150 MWac (1,575 MWp) portfolio (September 2024 JV)
International Green Loan: $1.36 billion secured (2023)
NTPC Renewable Energy Limited: Public Sector Leadership
NTPC REL Khavda Portfolio:
4,750 MW allocation across solar-wind hybrid zones
397.7 MW ground-mounted solar (Khavda Block-4) with NEXTracker solar trackers
Vikram Solar modules: 1,255 MW supply (bi-facial DCR modules, 540 Wp+, ALMM-compliant)
December 2024 Tender: 1,200 MW ISTS-connected solar (four 300 MW blocks)
Strategic Role:
Demonstrates Central Public Sector Undertaking (CPSU) commitment to renewables
Green Hydrogen Production: NTPC plans commercial-scale green hydrogen from Khavda power
Gujarat State Entities: GSECL & GIPCL
Gujarat State Electricity Corporation Limited (GSECL)
Allocation: 3,325 MW
Focus: Solar + wind hybrid to serve Gujarat's industrial demand
Status: Construction underway; commissioning expected 2025-26
Gujarat Industries Power Company Limited (GIPCL)
Allocation: 2,375 MW (solar-only zone)
Achievement: 50%+ completion with 315 MW operational (October 2025)
Timeline: 600 MW target by 2026
Economic Impact and Investment Case
Capital Expenditure: ₹1.5 Lakh Crore ($18-20 Billion USD)
Total Project Cost Breakdown:
Component | Estimated Cost (₹ Crore) | USD Equivalent |
Solar PV Modules & Mounting | 45,000 | $5.4 billion |
Wind Turbines & Foundations | 18,000 | $2.2 billion |
Transmission Infrastructure | 18,598 | $2.2 billion |
Battery Energy Storage (14 GWh) | 22,000 | $2.6 billion |
Civil Works & Roads | 8,000 | $960 million |
Grid Integration & Substations | 12,000 | $1.4 billion |
Land Lease & Clearances | 2,000 | $240 million |
O&M Contingency Reserve | 6,000 | $720 million |
Project Management & EPC | 18,402 | $2.2 billion |
Total | ₹150,000 crore | ~$18 billion |
Cost Benchmarking:
Per MW Cost: ₹5 crore/MW ($600,000/MW) — among world's lowest due to:
Domestic manufacturing under Production-Linked Incentive (PLI) schemes
Economies of scale (bulk procurement)
Zero land acquisition cost (government wasteland)
Funding Structure:
Developer Equity: 25-30%
Debt Financing: 70-75% (green bonds, multilateral loans, domestic banks)
Concessional Rates: 7-9% interest due to sovereign backing, green classification
Job Creation: Direct vs. Indirect Employment
Construction Phase (2020-2030):
Direct Jobs: ~100,000 workers
Civil construction: 40,000
Electrical installation: 25,000
Manufacturing (modules/turbines): 20,000
Project management/engineering: 5,000
Logistics & supply chain: 10,000
Operational Phase (post-2030):
Direct Jobs: ~15,200 permanent positions
Operations & Maintenance technicians: 8,000
Control room operators: 2,000
Security personnel (BSF-coordinated): 3,000
Administrative staff: 2,200
Indirect Employment:
Manufacturing Ecosystem: ~50,000 jobs in Gujarat's solar/wind manufacturing clusters (Dholera, Mundra)
Services Sector: ~25,000 in hospitality, transport, retail near Bhuj/Kutch towns
Economic Multiplier Effect:
₹12,000 crore (~$1.4 billion) in local procurement over 10 years
Infrastructure upgrades: 180 km fiber optic, 100+ km roads, water pipelines
Environmental Outcomes and Sustainability Indicators

Carbon Dioxide Offset: 50 Million Tonnes Annually
Emissions Avoidance Calculation:
Formula: CO₂ avoided = (Electricity generated × Grid emission factor)
Annual Generation: 81 billion kWh (81 TWh)
India Grid Emission Factor: 0.82 kg CO₂/kWh (2024)
CO₂ Avoided: 81,000,000,000 kWh × 0.82 kg/kWh = 66.42 million tonnes CO₂/year
Conservative estimates account for intermittency:
Adjusted Generation (considering 38% CUF): ~60-65 TWh/year
CO₂ Offset: 50 million tonnes/year
Contextualizing 50 Million Tonnes:
Equivalent to removing 10.8 million cars from roads
Equals annual emissions of Belgium (51 Mt CO₂)
15% of India's annual emission reduction target (1 billion tonnes by 2030)
Great Indian Bustard (GIB) Conservation: Balancing Development & Biodiversity
Background: The Great Indian Bustard (Ardeotis nigriceps) is critically endangered:
Population: <150 birds remaining
Primary Habitat: Grasslands of Rajasthan, Gujarat
Threat: Collisions with overhead power lines (poor frontal vision, heavy body)
Legal Framework:
2021 Supreme Court Order: Mandated undergrounding of all power lines in GIB habitats
March 2024 Revised Order: Balanced conservation with renewable energy goals:
Priority Areas: 14,013 sq km (Rajasthan) + 740 sq km (Gujarat)
Restrictions: No overhead lines >11 kV in priority zones
Mitigation: Bird diverters on existing lines, designated power corridors
Khavda Project Response:
Location Advantage: Khavda lies outside designated priority GIB zones
Transmission Design: Underground cables for last-mile connectivity near sensitive areas
Monitoring: Wildlife Institute of India (WII) oversight
Broader Biodiversity Concerns: Environmental groups flag:
Salt Desert Ecosystem: Unique flora/fauna (flamingos, desert foxes, migratory birds)
No Environmental Impact Assessment (EIA): Large renewable projects exempted since 2022
Cumulative Impact: Multiple mega-projects in Kutch (solar, wind, cement, ports)
Developer Commitments:
Habitat Restoration: Funding for grassland conservation programs
Eco-sensitive Zone Management: Buffer zones around park boundaries
Water Conservation: Dry Cleaning vs. Robotic Systems
Challenge: Dust accumulation in arid desert reduces panel efficiency by 15-25%
Traditional Cleaning:
Water Requirement: 7,000-20,000 liters/MW/cleaning cycle
Frequency: Twice/week in desert = ~1.5 million liters/MW/year
Khavda Innovation — Waterless Robotic Cleaning:
Technology: Automated brush systems with airflow/electrostatic dust removal
Water Savings: 100% elimination = conserves ~45 billion liters/year for 30 GW
Cost: ₹12-15 lakh/MW upfront vs. ₹3-5 lakh/MW/year ongoing water costs
ROI: 3-4 years payback
Environmental Benefit:
Supports UN SDG 6 (Clean Water & Sanitation)
Critical in water-scarce Kutch (annual rainfall <400 mm)
Storage & Grid Stability Outlook
14 GWh Battery Storage: Turning Intermittency into Dispatchability
Problem Statement: Solar/wind generation is non-dispatchable (weather-dependent):
Solar: 0% output at night
Wind: Fluctuates hourly
Grid Requirement: Stable, predictable supply matching demand curve
Solution — Battery Energy Storage Systems (BESS):
Government Plan:
14 GWh grid-scale BESS for Khavda (announced in project plans)
Purpose: Load shifting, frequency regulation, peak shaving
Adani Green Energy BESS Deployment:
Parameter | Value |
Phase 1 Capacity | 1,126 MW / 3,530 MWh |
Commissioning | March 2026 |
Technology | Lithium-ion batteries with EMS (Energy Management Systems) |
Configuration | 700+ BESS containers |
Cost | ~₹3,500 crore ($420 million) |
Future Scale-up | 15 GWh by FY2027; 50 GWh within 5 years |
Operational Benefits:
Energy Arbitrage: Store cheap midday solar → dispatch during peak evening demand (6-10 PM)
Grid Stability: Fast-response (<100 ms) frequency regulation
Transmission Congestion Relief: Local storage reduces evacuation bottlenecks
Curtailment Reduction: Absorbs excess generation during high wind/solar periods
Economic Value:
Peak Power Premium: ₹8-12/kWh (peak) vs. ₹2-3/kWh (off-peak)
Revenue Enhancement: 40-60% improvement in project IRR with co-located storage
India's Broader BESS Roadmap:
Current: ~0.5 GWh operational BESS capacity (as of April 2025)
Target (2031-32): 236.22 GWh BESS + 175.18 GWh pumped hydro = 411.4 GWh total
Technical & Operational Challenges
Harsh Environment: Salt Corrosion, Sandstorms, and Logistical Nightmares
Environmental Stressors:
1. High Salinity & Corrosion
Salt Content: Rann of Kutch soil contains 35-45% sodium chloride
Impact: Accelerated corrosion of:
Steel structures (module mounting, turbine towers)
Electrical connections (contacts, terminals)
Inverters and transformers (enclosures)
Solution:
Hot-dip galvanization (minimum 120 microns coating)
Galvalume steel for long-term durability
Marine-grade stainless steel for critical components
2. Saline Groundwater
Challenge: Water table at 15-20 meters depth contains dissolved salts
Construction Impact: Concrete foundations require sulfate-resistant cement
Mitigation: Underground stone columns (Adani innovation) to enhance load-bearing capacity
3. Extreme Temperatures
Summer: 46-48°C (115-118°F) peaks
Winter: 2-5°C (35-41°F) with frost
Impact:
Module efficiency drops 0.4-0.5%/°C above 25°C
Thermal expansion/contraction stress on structures
Design Response:
Bi-facial modules capture reflected heat (albedo effect)
High-temperature rated cables (up to 90°C)
4. Dust Storms & Sand Accumulation
Frequency: 50-70 dust storms/year
Sand Deposition: 2-3 kg/m²/day on horizontal surfaces
Efficiency Loss: Uncleaned panels lose 20-30% output within 2 weeks
Solution: Waterless robotic cleaning (deployed 3-4 times/week)
5. Seismic Activity
Location: Kutch falls in Seismic Zone IV (high-risk)
Historical Event: 2001 Bhuj earthquake (7.7 magnitude, 20,000+ deaths)
Design Code: IS 1893 (Earthquake-resistant structures)
Foundation: Reinforced concrete with seismic buffers
Grid Integration Bottlenecks
Current Constraints (2025):
Challenge | Impact | Resolution Timeline |
Transmission Capacity | Limited to 5-7 GW evacuation | Phase-2 lines by 2026-27 |
Substation Availability | Pooling station congestion | 3 new 765 kV substations under construction |
Voltage Fluctuation | ±5% variance during peak generation | STATCOM installation (2025-26) |
Grid Code Compliance | Fault ride-through, frequency response | Advanced inverters with grid-forming capability |
Short-Term Workaround:
Curtailment: 5-10% of generation curtailed during high-wind periods (lost revenue: ~₹200-300 crore/year)
Battery Storage: BESS deployment absorbs curtailed energy
Long-Term Solution (2027-2032):
Dedicated HVDC Link: Khavda → Delhi/Mumbai (2,000+ km, ₹15,000 crore)
Smart Grid: AI-based demand forecasting, dynamic pricing
Workforce & Logistics Challenges
Remote Location:
Distance from Bhuj: 70 km
Nearest Railway: ~100 km (Gandhidham)
Port Access: ~150 km (Mundra Port for equipment import)
Worker Housing:
Temporary Camps: 4,000+ workers housed in makeshift facilities (as of 2023-24)
Turnover: High attrition due to:
Harsh living conditions
Lack of mobile connectivity (limited tower infrastructure)
Isolation from families
Security Concerns:
Border Proximity: 1 km from Pakistan border
BSF Coordination: Border Security Force clearances required for personnel
Background Checks: Stringent vetting to prevent infiltration risks
Equipment Transport:
Wind Turbine Blades: 60-70 meters long — require specialized trailers, road widening
Heavy Transformers: 200-300 tonnes — challenge for local road infrastructure
Comparisons – Gujarat Hybrid Park vs Other Global Projects
Khavda vs. Bhadla Solar Park (India)
Parameter | Khavda Hybrid RE Park | Bhadla Solar Park (Rajasthan) |
Capacity | 30,000 MW (26 GW solar + 4 GW wind) | 2,245 MW (solar only) |
Technology | Hybrid (solar + wind) | Pure solar |
Land Area | 72,600 hectares | 14,000 acres (~5,666 hectares) |
Location | Kutch, Gujarat (coastal influence) | Thar Desert, Rajasthan |
Solar Irradiation | 2,060 kWh/m²/year | 2,300 kWh/m²/year (higher) |
Investment | ₹150,000 crore ($18 billion) | ₹14,000 crore ($1.6 billion) |
Operational Status | ~5,355 MW (as of 2025) | Fully operational (2,245 MW) |
Commissioning Year | 2020-2030 (phased) | 2015-2020 (4 phases) |
Key Innovation | Waterless cleaning, 14 GWh BESS | Ultra-low tariffs (₹2.44/kWh bid in 2017) |
Developer Model | Multi-developer (6 entities) | Multi-developer |
Verdict: Bhadla pioneered India's utility-scale solar with record-low tariffs. Khavda scales this 13x with hybrid technology and storage.
Khavda vs. Gonghe Talatan Solar Park (China)
Parameter | Khavda Hybrid RE Park | Gonghe Talatan Solar Park (China) |
Capacity | 30,000 MW (26 GW solar + 4 GW wind) | 15,600 MW (solar only) |
Technology | Hybrid (solar + wind + storage) | Pure solar |
Land Area | 726 sq km | ~345 sq km |
Location | Kutch, Gujarat (sea-level) | Qinghai Province (~3,000m altitude) |
Annual Generation | 81 TWh (estimated) | ~17.9 TWh (actual) |
Investment | $18 billion | $7.2 billion (estimated) |
Operational Status | ~18% commissioned | Fully operational |
Commissioning | 2020-2030 | 2011-2024 (phased) |
Modules Deployed | 55 million (planned) | ~7.2 million |
Analysis:
China's Advantage: Faster execution (13 years), established supply chains
India's Edge: Hybrid model (continuous generation), lower labor costs
Key Differentiator: Khavda's 30 GW = 2x Gonghe — will become undisputed #1
Establishing Khavda as Clear #1
Current World Rankings (Operational Capacity, 2025):
Gonghe Talatan Solar Park (China): 15,600 MW
Urumqi Midong Solar Park (China): 3,500 MW
Mohammed bin Rashid Al Maktoum Solar Park (UAE): 3,660 MW (various phases)
Bhadla Solar Park (India): 2,245 MW
Pavagada Solar Park (India): 2,050 MW
Projected Rankings (2030, post-completion):
Khavda Hybrid RE Park (India): 30,000 MW ← NEW #1
Gonghe Talatan (China): 15,600 MW (may expand)
Urumqi/Midong (China): ~10,000 MW (planned expansion)
Mohammed bin Rashid (UAE): 5,000 MW (Phase 5 completion)
Ladakh Renewable Energy Park (India): 5,000 MW (planned)
Khavda's Unique Claim:
Largest single-location hybrid (solar + wind)
Largest co-located storage (14+ GWh BESS)
Visible from space (once complete)

Frequently Asked Questions
Q1. What is the capacity of the Gujarat Hybrid Renewable Energy Park?
Answer: The Gujarat Hybrid Renewable Energy Park has a planned capacity of 30,000 megawatts (30 GW), comprising 26,000 MW of solar power and 4,000 MW of wind power.
This makes it the world's largest renewable energy installation by capacity. As of February 2025, approximately 5,355 MW has been commissioned by lead developer Adani Green Energy Limited, with full completion targeted for 2030. The hybrid configuration allows continuous generation throughout the day and night, maximizing land utilization and grid stability.
Q2. How does the hybrid solar + wind model improve energy reliability?
Answer: The hybrid solar + wind model at Khavda improves energy reliability through complementary generation patterns—solar panels produce peak power during midday when the sun is strongest, while wind turbines generate maximum output during evening and nighttime hours when coastal thermal gradients are most active.
This temporal diversity results in:
38-42% capacity utilization factor (compared to 23-25% for standalone solar or 30-35% for standalone wind)
Reduced intermittency: Gaps in solar generation are filled by wind, and vice versa
Smoother grid integration: Combined output has lower variance than single-source generation
Enhanced economics: Higher CUF means more revenue per MW installed capacity
When paired with the planned 14 GWh battery energy storage system (BESS), the park will approach firm and dispatchable renewable energy (FRE/DRE) status, enabling 24/7 clean power delivery to match demand patterns.
Q3. Which companies and agencies are executing the project?
Answer: The Gujarat Hybrid Renewable Energy Park is a multi-developer project coordinated by the Gujarat Government, with capacity allocated among six primary entities:
Adani Green Energy Limited (AGEL): 9,500 MW – Largest private developer with 5,355 MW operational (as of 2025)
Sarjan Realities Pvt. Ltd.: 4,750 MW – Private developer, construction underway
NTPC Renewable Energy Limited: 4,750 MW – Public sector leader with 212.5 MW operational
Gujarat State Electricity Corporation (GSECL): 3,325 MW – State utility
Gujarat Industries Power Company Limited (GIPCL): 2,375 MW – State entity with 315 MW operational
Solar Energy Corporation of India (SECI): 3,000 MW – Conducts competitive bidding for wind-only zone
Supporting agencies include:
Ministry of New and Renewable Energy (MNRE): Policy oversight
Power Grid Corporation of India (PGCIL): Transmission infrastructure
Gujarat Urja Vikas Nigam Limited (GUVNL): Power purchase and state coordination
Ministry of Defence: Security clearances (border proximity)
Q4. How will this project impact India's renewable energy goals?
Answer: The Khavda project is a cornerstone of India's 500 GW by 2030 renewable energy target:
Contribution: 30 GW = 6% of India's total 500 GW commitment
Gap Closure: Addresses 10.6% of the remaining 282.38 GW needed by 2030
Accelerated Pace: Single-location project adding ~4-5 GW/year during peak construction
Broader Impacts:
Manufacturing Boost: PLI scheme drives domestic solar module production from 38 GW (2024) → 74 GW (2025)
Energy Security: Reduces coal imports by $2.5 billion/year
Carbon Neutrality: 50 million tonnes CO₂ avoided annually = 15% of India's 2030 emission reduction target
Global Leadership: Positions India as 4th largest renewable capacity (after China, USA, Germany)
Precedent Setting: Demonstrates viability of wasteland-based mega parks, replicable in other arid regions (Ladakh, Rajasthan)
Q5. What environmental benefits does the park deliver?
Answer: The Gujarat Hybrid Renewable Energy Park provides substantial environmental benefits once fully operational:
Carbon Emissions Reduction:
50 million tonnes CO₂ avoided annually (equivalent to removing 10.8 million cars)
Coal displacement: 60,300 tonnes/day not burned
Air quality improvement: Zero SOx, NOx, particulate emissions (unlike thermal plants)
Water Conservation:
45 billion liters/year saved through waterless robotic panel cleaning systems
Critical in water-scarce Kutch region (annual rainfall <400 mm)
Land Use Optimization:
Wasteland reclamation: Converts 72,600 hectares of salt desert (unsuitable for agriculture) into productive asset
Minimal habitat disruption: Located outside Great Indian Bustard priority conservation zones
Biodiversity Mitigation:
Underground transmission cables in eco-sensitive corridors
Bird diverters on overhead lines
Habitat restoration funding for grassland conservation
Circular Economy:
85-90% of solar modules/wind turbines recyclable post-lifespan
Local procurement of 40-50% components (reduces transport emissions)
Q6. What role does energy storage play in hybrid parks?
Answer: Energy storage is critical for transforming intermittent solar/wind generation into reliable, dispatchable power:
Primary Functions:
Load Shifting: Store excess midday solar → dispatch during evening peak demand (6-10 PM)
Frequency Regulation: Rapid response (<100 milliseconds) stabilizes grid frequency (50 Hz ± 0.2 Hz)
Voltage Support: Provides reactive power for grid stability
Curtailment Reduction: Absorbs generation during low-demand periods (prevents waste)
Transmission Congestion Relief: Local storage reduces need for long-distance power evacuation
Khavda Storage Roadmap:
Government Plan: 14 GWh grid-scale BESS (announced)
Adani Deployment: 3.53 GWh by March 2026 (Phase 1)
Future Scale: 15 GWh by FY2027; 50 GWh within 5 years
Economic Impact:
Revenue Enhancement: Peak power tariffs (₹8-12/kWh) vs. off-peak (₹2-3/kWh) = 40-60% IRR improvement
Grid Services Revenue: Ancillary services market (frequency regulation) pays ₹1-2/kWh
Technology:
Lithium-ion batteries (90-95% round-trip efficiency)
Energy Management Systems (EMS): AI-based dispatch optimization
Containerized Design: Modular scalability, rapid deployment
India's Storage Gap:
Current: ~0.5 GWh operational (as of 2025)
Requirement (2031-32): 236.22 GWh BESS + 175.18 GWh pumped hydro = 411.4 GWh
Khavda's Contribution: 14 GWh = 6% of 2032 BESS target
Bottom Line: Without storage, hybrid parks achieve only 38-42% capacity utilization. With storage, they approach 60-70% effective utilization, becoming firm renewable energy (FRE) sources that can replace baseload coal plants.
Conclusion
The Gujarat Hybrid Renewable Energy Park stands as a testament to India's renewable energy ambition—a 30 GW colossus rising from the salt deserts of Kutch that will redefine global clean energy benchmarks.
This is not merely infrastructure; it is a blueprint for transforming marginal land into economic and environmental assets, demonstrating that decarbonization and development are not opposing forces but complementary imperatives.
Key Takeaways:
Unprecedented Scale: At 30,000 MW, Khavda will be 2x larger than any existing renewable park globally, generating 81 TWh annually—enough to power 18 million homes or entire nations like Belgium.
Hybrid Innovation: The 26 GW solar + 4 GW wind configuration achieves 38-42% capacity utilization through complementary generation patterns, far exceeding standalone installations.
Strategic Contribution: Khavda delivers 6% of India's 500 GW by 2030 target from a single location, demonstrating that giga-scale projects can accelerate national transitions faster than diffuse installations.
Carbon Impact: 50 million tonnes CO₂ avoided annually = removing 10.8 million cars or 15% of India's 2030 emission reduction goal under Paris Agreement.
Economic Transformation: ₹150,000 crore ($18 billion) investment generates 100,000+ jobs, displaces $2.5 billion/year in coal imports, and catalyzes Gujarat's manufacturing ecosystem.
Technical Excellence: Innovations like waterless robotic cleaning (saving 45 billion liters/year), underground stone columns for saline soil, and 14 GWh BESS deployment showcase engineering adaptability to extreme environments.
Balanced Development: Despite legitimate concerns around biodiversity (Great Indian Bustard) and EIA exemptions, the project navigates these complexities through designated transmission corridors, Supreme Court-mandated mitigation, and strategic siting outside priority conservation zones.
Challenges Ahead:
Grid Integration: Current 5-7 GW evacuation capacity constrains dispatch until 2026-27 transmission upgrades complete
Storage Deployment: 14 GWh BESS installation is capital-intensive (~₹22,000 crore); phased commissioning required
Workforce Retention: Harsh conditions, remote location demand better worker facilities
Environmental Vigilance: Long-term monitoring needed for cumulative ecosystem impacts
Global Implications:
Khavda's success (or failure) will influence renewable megaprojects worldwide. It demonstrates that:
Wasteland is not waste: Salt deserts, cold deserts (Ladakh), arid zones can become energy hubs
Hybrid > Single-Source: Combining solar + wind + storage maximizes land ROI and grid stability
Speed Matters: 10-year execution (2020-2030) proves emerging economies can match China's infrastructure velocity
Policy Enablers: Land allocation frameworks, transmission coordination, PLI manufacturing incentives are replicable
The Path Forward:
India aims to operationalize 60-70 GW/year additions through 2030. If Khavda scales from 5.4 GW (2025) → 30 GW (2030) on schedule, it validates the feasibility of 5+ similar projects (Ladakh 5 GW, Rajasthan expansions, offshore wind). This cascading effect could position India to exceed its 500 GW commitment by 2028-29, not 2030.
The Gujarat Hybrid Renewable Energy Park is more than infrastructure—it is a forcing function for India's energy independence, a laboratory for global decarbonization strategies, and a symbol that the 21st century's energy superpowers will be defined not by fossil reserves, but by renewable ambition and execution capability.
References & Data Sources
This article is backed by authoritative sources and research from the following organizations and government agencies:
Government & Policy Sources:
Ministry of New and Renewable Energy (MNRE), Government of India
India's Renewable Energy Capacity Achieves Historic Growth in FY 2024-25
Press Information Bureau, Government of India
Government declares plan to add 50 GW of renewable energy capacity annually
https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=1913789
Press Information Bureau, Government of India
The Solar Surge: India's Bold Leap Toward a Net Zero Future
Press Information Bureau, Government of India
India achieved Historic milestone in power sector: Surpasses 500 GW
Ministry of Power, Government of India
India's Renewable Energy Revolution
https://www.pib.gov.in/PressReleaseIframePage.aspx?PRID=2094992
Gujarat Power Corporation Limited (GPCL)
Gujarat Solar/Wind Hybrid RE PARK (30 GW) Project Information
International Organizations:
International Energy Agency (IEA)
Renewables 2024 Report
International Renewable Energy Agency (IRENA)
Renewable Capacity Statistics 2025
Wikipedia - Gujarat Hybrid Renewable Energy Park
Comprehensive project overview with citations
https://en.wikipedia.org/wiki/Gujarat_Hybrid_Renewable_Energy_Park
Wikipedia - Renewable energy in India
National renewable energy progress tracking
Industry & Developer Sources:
Adani Green Energy Limited (AGEL)
Adani Green Begins Generation From The World's Largest Renewable Energy Park
Business Standard
Adani Group plans to build India's largest battery storage system
BlackRidge Research
World's Biggest 30 GW Gujarat Hybrid Renewable Energy Park
BlackRidge Research
Top Upcoming Renewable Energy Projects in India (2025)
BlackRidge Research
Bhadla Solar Park: The Largest Solar PV Power Plant Project
Media & Analysis:
Dwello
Khavda Renewable Park: The 30 GW Project Transforming India's Energy Landscape
https://dwello.in/news/khavda-renewable-park-the-30-gw-project-transforming-indias-energy-landscape
Construction Review Online
World's Largest Renewable Energy Park Project Achieves Significant Milestone
Elets Technomedia
Khavda Powering 18 Million Household with Solar and Wind Energy
Das Energie
Khavda Solar Park: Boosting India's Solar Landscape
Interesting Engineering
World's 10 biggest solar power projects transforming energy future
https://interestingengineering.com/energy/world-10-biggest-solar-power-projects
SolarQuarter
India Crosses 505 GW Installed Power Capacity
SolarQuarter
Supreme Court Orders Strong Conservation Measures For Great Indian Bustard
APAC News Network
Adani Group Launches 3,530 MWh Battery Storage Project at Khavda
Outlook Business
Why Adani's Plans for a Battery Storage System Mark a Turning Point
Chemical Industry Digest
AGEL to Scale Up Battery Storage at Khavda, Gujarat
https://chemindigest.com/agel-to-scale-up-battery-storage-at-khavda-gujarat/
Environmental & Conservation:
Baker McKenzie
What Does a Critically Endangered Bird Have to do With India's Energy Transition?
https://www.bakermckenzie.com/en/insight/publications/2024/06/india-energy-transition
Word of India
India's Power Corridors to Save Great Indian Bustard
https://wordofindia.com/great-indian-bustard-power-corridors-2024/
Sanskriti IAS
Saving the Great Indian Bustard: Supreme Court's Conservation–Energy Balance
Insights on India
Great Indian Bustard & Green Energy Corridor Explained
https://www.insightsonindia.com/2025/12/22/great-indian-bustard-2/
The Press Pad
Great Indian Bustard Conservation: Renewable Energy Development with Habitat Protection
Technical & Academic:
PV Tech
NTPC Green commissions 212.5MW of 1.2GW Khavda PV plant in Gujarat
https://www.pv-tech.org/ntpc-green-commissions-212-5mw-of-1-2gw-khavda-pv-plant-in-gujarat/
Global Energy Monitor
Power Sector Transition in Gujarat
India Brand Equity Foundation (IBEF)
India's Renewable Energy Growth: Solar Power & More
Energetica India Magazine
India Surges to 217.62 GW Renewable Energy Capacity, Targets 500 GW by 2030
Down To Earth
India's Ambitious 500 GW Clean Energy Target by 2030: A Deep Dive
https://www.downtoearth.org.in/energy/the-500-gw-switch-over
International Media:
Arab News
In the salt deserts bordering Pakistan, India builds its largest renewable energy project
Asia Renewable Energy
Asia's Giga-Project: Gujarat Hybrid Renewable Energy Park
https://www.renewableenergyasia.org/2025/11/asias-giga-project-gujarat-hybrid.html
Other Relevant Sources:
SolarSquare
Bhadla Solar Park in Rajasthan
Solar Tech Online
World's Largest Solar Farms 2025: Complete Guide
https://solartechonline.com/blog/largest-solar-farms-world-2025/
Wikipedia - Bhadla Solar Park
Comprehensive technical details and history
Realty Today
India's Khavda Renewable Energy Park: The World's Largest Solar and Wind Power Project
KPI Green Energy
Khavda Solar Project Success Story
https://www.kpigreenenergy.com/blog/khavda-solar-project-case-study
Utkarsh Current Affairs
World's largest renewable energy park being built in Gujarat
https://utkarsh.com/current-affairs/worlds-largest-renewable-energy-park-being-built-in-gujarat
The Secretariat
Gujarat's Green Energy Vision Advances With Khavda Wind-Solar Hybrid Park
Vajir am & Ravi IAS Academy
Khavda Renewable Energy Park - Current Affairs
https://vajiramandravi.com/current-affairs/khavda-renewable-energy-park/
Disclaimer:
This case study is compiled for educational and informational purposes based on publicly available data as of February 2025. While every effort has been made to ensure accuracy through verification with authoritative sources, renewable energy projects are dynamic with frequent updates to capacity, timelines, and technical specifications.
The financial projections, carbon offset calculations, and economic impact assessments represent estimates derived from industry standards and may vary based on actual operational performance, policy changes, and market conditions.
This article does not constitute investment advice, legal counsel, or official guidance from any government agency or corporate entity. Readers are encouraged to consult official sources (MNRE, SECI, Adani Green Energy, NTPC) for the most current project information.
The analysis of environmental impacts, including Great Indian Bustard conservation, reflects the regulatory framework as of the latest Supreme Court orders (2024-2025) and may be subject to judicial review or policy amendments.
Views expressed regarding comparisons with international projects (China's Gonghe Talatan, UAE's Mohammed bin Rashid Al Maktoum Solar Park) are based on publicly reported data and independent analysis.
© Green Fuel Journal Research Division | Published: February 2026